Service line map · Illustrative case

Tarnlea Bio: five workstreams from stealth to first contract

Dr Ishbel Nairn (fictional) is taking the TarnCell digester from stealth to a first commercial contract. Each line is a workstream in her journey. The zones are the five phases of the support map, and the stations are the 20 stages of the tracker, numbered as in the tracker. Where workstreams share a stage, the station becomes an interchange.

Illustrative, hypothetical example 5 workstreams · 20 stages · 124 steps · 13 interchanges · 3 exits
The map

Five workstreams across five phases

Follow a line left to right. Select a station name to open its steps below, and use the controls to see the whole map or read it closely.

Drag or scroll inside the sheet to move around
SENSE CHECK FEASIBILITY EARLY R&D SCALING COMMERCIALISATION What outsiders can see Confidential: NDAs and private advice Partly visible: awards, permits, patent publication Public Scottish Enterprise account lead (persona) Iain Robertson: innovation and R&D Sarah Menzies: finance and investment Fiona MacLeod: growth and scale-up I I Distillery's effluent question F F Account plan sets the order D D Founding in stealth C C Effluent costs at the host R R Feedstock and land checks Moveable kit excluded by ZWS: reframe, or SE feasibility fund Misses the IBioIC call: voucher or SE feasibility fund Host withdraws: move the pilot to the fallback host 1 Incorporate in stealth NDAs, IP assigned 2 Talk to SE in confidence with Business Gateway Feasibility fund date still unclear 3 File UK priority patent starts the stealth clock Publishes 18 months after filing 4 Map feedstock and land GIS, gas grid, NVZs 5 Secure university partner Interface and a voucher Publication rights clash with stealth 6 Run bench trials pot ale and lees 7 Talk to SEPA early waste or by-product? 8 Apply for ZWS and SE grants paid in arrears Costs paid upfront, claimed back later 9 Commission IBioIC study scale-up risks 10 Build the pilot unit Moray fabrication partner Pilot sits in a second agency's area 11 Secure pilot permissions SEPA, effluent, DSEAR, planning Register entries end stealth 12 Raise the seed round angels, EDGE, SCF match 13 Place a KTP associate plus R&D tax relief 14 Run the 12-month pilot biogas displaces boiler fuel Pilot tied to the silent season 15 Certify digestate to PAS 110 SEPA end of waste 16 Design for manufacture SMAS and NMIS 17 Open SNIB and IFS talks unit finance SNIB needs revenue and scale first 18 Public launch exit stealth 19 First commercial contract distillery group 20 Test Irish and Nordic markets with SDI and UKEF Key I Innovation and R&D F Funding and investment D IP and stealth disclosure C Circular economy, energy and water R Regulation and permissions Stop (action) Event Interchange: routes share a step Terminus: outcome or end Friction Exit or signpost out Assumed, not evidenced Service line map after the tube-map journey method of Stéphanie Krus (Scottish Enterprise design blog, 2020) and the Miroverse Tube Map template by David O'Brien. Built with service-line-maps, The Strategy CaFE. Based on the Tarnlea Bio AD Support Map and tracker.
What the map shows

Four things to take into the room

These come from the map's pattern scan. They are prompts for discussion, not findings from research.

Disclosure

Stealth runs the whole length of the journey

The IP and stealth disclosure line touches 10 of the 20 stages and carries 5 of the 8 friction points. Move: keep one disclosure plan, dated against the patent's publication, and review it at every interchange on the D line.

Interchanges

Six stages carry three or more workstreams

Stages 2, 8, 11, 15 and 19 each serve three workstreams, and stage 20 serves four. A delay at any of them is felt on every line through it. Move: name one owner for each of these stages.

Regulation

The shortest line meets the most public moments

Regulation and permissions has only 5 stops, but stages 11 and 15 put permits and certified status on the public record. Move: time those submissions against the disclosure plan, not the build plan.

Ownership

No account lead at the very first stage

Incorporation happens before a Scottish Enterprise account manager is in place, which is the one gap in the bottom band. Move: use Business Gateway and the strategy adviser to cover stage 1, and open the account conversation early.

Phases, stages and steps

Stages and steps

The 20 stages and 124 steps from the project tracker, grouped by phase. Filter by workstream to see only the stages on that line.